Summary Progress Produksi

8
Total Proyek
62%
Rata-rata Progress
0
Proyek Selesai
0
Total Unit

Detail Progress Proyek

No Nama Proyek Qty Progress Status Catatan
1 PT.BTS - Pengadaan Bracket Arm Support & Bracket Arm Pole 2m -
91%
Berlangsung
2 PT. BTS - BRACKET CCTV SMART EYE -
88%
Berlangsung
3 PT. INTEGRASI JARINGAN EKOSISTEM - CABINET 42U FAN (50 Unit) -
99%
Berlangsung
4 ABADI JAYA BERSAMA - RACK INVERTER (2000 UNIT) -
7%
Berlangsung
5 PT. INTEGRASI JARINGAN EKOSISTEM - CABINET 5U Inc Bracket (200 Unit) -
88%
Berlangsung
6 PT. STARCOM - Mini Pole Alligment 4M (2Unit) -
80%
Berlangsung
7 PT. INFRATECH - Safety Ladder 7M & 2M -
33%
Berlangsung
8 Papa Energi Mandiri - Walkway 38 unit -
7%
Berlangsung